To Canoas

3108ToCan01

3108ToCan02

3108ToCan03

3108ToCan04

3108ToCan05

3108ToCan06

3108ToCan07

3108ToCan08

3108ToCan09

3108ToCan10

3108ToCan11

3108ToCan12

Quito to Bahia



3008ToBah

Mariposario, Mindo

2908Mari01

2908Mari02

2908Mari03

2908Mari04

2908Mari05

2908Mari06

2908Mari11

2908Mari07

2908Mari12

2908Mari09

2908Mari10

Nariz del Diablo

2608Tren01

2608Tren02

2608Tren03

2608Tren04

2608Tren05

2608Tren06

2608Tren07

2608Tren08

2608Tren09

2608Tren10

2608Tren11

2608Tren12

2608Tren13

2608Tren14

2608Tren15

2608Tren16

2608Tren17

2608Tren18

2608Tren19

2608Tren20

2608Tren21

2608Tren22

2608Tren23

2608Tren24

2608Tren25


2608Tren26

2608Tren27

2608Tren28

2608Tren29

Cotopaxi and Banos



2508CotoP01

2508CotoP02

2508CotoP03

2508CotoP04

2508CotoP05

2508CotoP06

2508CotoP07

2508CotoP08

2508CotoP09

2508CotoP10

2508CotoP11

2508CotoP12

2508CotoP13

2508CotoP14

2508CotoP15

2508CotoP16

2508CotoP17

2508CotoP19

2508CotoP20

2508CotoP22

2508CotoP23

2508CotoP24

2508CotoP25

2508CotoP26

2508CotoP272508CotoP28



2508CotoP30

2508CotoP31

2508CotoP32

2508CotoP33

2508CotoP34

2508CotoP35

2508CotoP36

2508CotoP37

2508CotoP38

2508CotoP39


2508CotoP40

2508CotoP41

2508CotoP42

2508CotoP43

2508CotoP44

2508CotoP45

2508CotoP46

Pinchincha

2408Pinch01

2408Pinch02

2408Pinch03

2408Pinch04

2408Pinch05

2408Pinch06

2408Pinch07


2408Pinch09

2408Pinch10

2408Pinch13

2408Pinch18

2408Pinch23

2408Pinch24

2408Pinch27

2408Pinch34

2408Pinch35

2408Pinch38

2408Pinch43

2408Pinch47

2408Pinch51

2408Pinch52

2408Pinch55

2408Pinch56

2408Pinch57

2408Pinch60

2408Pinch61

2408Pinch63

2408Pinch65

2408Pinch66

Cumbaya

2308Kibb01

2308Kibb02

2308Kibb03

Quito - Centro Colonial

2208CC01

2208CC02

2208CC03

2208CC04

2208CC05

2208CC06

2208CC07

2208CC08

2208CC09

2208CC10


2208CC11

2208CC12

2208CC13

2208CC14

2208CC15

2208CC16

2208CC17

2208CC18

2208CC19

2208CC20

2208CC21

2208CC22

Otavalo

2108Kibb01

2108Kibb02

2108Kibb04



2108Kibb07

2108Kibb11

2108Kibb13

2108Kibb16


2108Kibb20

2108Kibb23

Cayambe and Ibarra

2008Cay01

2008Cay02

2008Cay03

2008Cay04

2008Cay05

2008Cay06

2008Cay07

2008Cay08

2008Cay09

2008Cay10

2008Cay11

2008Cay12

2008Cay13

2008Cay14

2008Cay15

2008Cay16

2008Cay17

2008Cay18

2008Cay19

2008Cay20

2008Cay21

2008Cay22

Mitad del Mundo

Another lovely sunny morning. My day started with a visit to Movistar. Due to a network software implementation problem my new phone would not work. Don't worry they said, it will be working in 4 hours.

We had lunch at the El Bosque centre overlooking Quito airport.
1908MM01

Afterwards we visited Mitad del Mundo just north of Quito. This monument was completed in 1982, and marks a point on the equator. The 4.5 metre sphere on top weighs 5 tons.
1908MM02

Smaller towers on each side of the monument give position and altitude.
1908MM031908MM04

Nancy straddling the equator. However, using WGS84 datum, she isn't. That datum places the equator 240m further north.
1908MM05

The yellow line was marked using a different datum in use in Ecuador in 1982.
1908MM06

Facing west. Don't try this at sea.
1908MM07

Further north and west the road drops down into temperate rainforest, often obscured by clouds.
1908MM08

Returning to Quito from the north with and afternoon thunderstorm looming.
1908MM09

Back in Quito it rained heavily at around 17:00. As usual.

Quito Parque la Carolina

Parque la Carolina in the centre of Quito.

1808Qui01

1808Qui02

1808Qui03

Piriapolis - Launch Day

An absolutely perfect day for launching. Flat calm, sunny and no wind.

I had been told to be on hand at 08:30. I was, but nobody else was there. Around 08:45 Walter, the yard manager showed up and asked if we were ready to go. We were.

Bow at haul out in May...
1108B4

About 3cm of red gelcoat at the waterline was ground back to the laminate and replaced by epoxy, effectively raising the waterline by 3cm.

...and today.
1108Aft

Travel lift moving into position at 09:10.
1108LD01

Slings on and weight taken. The slings here are not particularly clean and marked the topsides during haul out. I took the precaution of having some thick plastic sheeting on hand to wrap the slings. Steel sling pins were also a hazard so Laurence wrapped them in cloth.
1108LD02

Last minute touching up of prop spots and keel base.
1108LD03

09:45 and we were all set.
1108LD04

This is a 90 ton travel lift. Kiriwina is around 4.5 tons.
1108LD05

Lining Up.
1108LD06

In we go.
1108LD07
1108LD08

Laurence and some of the Hidrografia team.
1108LD09

Ian and Elisa, our port crew.
1108LD10

A very tranquil Piriapolis harbour.
1108LD11

Launching dock.
1108LD12

A photo opportunity with the skipper. At this point we were shipping water rather faster than was desirable. The cause, discovered later, was a pre-launch dummy log placement malfunction.
1108LD13

All fast in our allocated berth at 10:20. This was well into the harbour and more sheltered than our berth in May. Stern buoys were much closer to the dock making for a much better and more secure mooring
1108LD14

Kiriwina lying safely in her berth. She will spend 6-9 weeks here before we return to Brazil in the spring.
1108LD15

Piriapolis waterfront at 22:45. Sea calm. Wind zero knots.
1108LD16

Piriapolis Boatyard Day 20

Definitely the final day in the boatyard.

We were in the yard early and ready to launch in moderate weather conditions. Sadly, a large supply vessel launched yesterday had suffered an engine malfunction and was unable to move from the haul out dock.

It eventually sailed around 13:00 but by then the wind had increased and the travel lift crew had disappeared. They were not seen for the rest of the day. Tango India Uniform.

Never mind. We used the extra time to complete some gelcoat repairs and in another outbreak of mission creep embarked on a few more.

Elisa drying some gelcoat.
1008Egd

Since I took delivery of Kiriwina in 2005 there have been a number of gelcoat flaws. This one is on the bridge deck.
1008GC01.1

The cause is space between gelcoat and laminate. When the laminate is applied during construction gaps can be left when the laminate is not properly laid onto gelcoat. This is more likely to occur in tight spaces.

A close up on the bridge deck. Loose gelcoat has been partially ground away to expose the laminate.
1008GC01

Laurence wielding his Dremel with surgical precision. Elisa is hoovering the dust.
1008GC04

Ready for new geloat.
1008GC03

Here the problem is repeated in the cockpit adjacent to the fuel filler. Back in 2006 a similar problem developed at the mast heel.
1008GC05

Cleaned up and ready for new gelcoat.
1008GC06

And again. This time in the starboard forward cockpit corner.
1008GC07

Ready.
1008GC08

I did this. Holes to mount a support pole for the Superwind. Arrangement did not work and was abandoned in favour of an A frame.
1008GC09

Dremeled.
1008GC10

Piriapolis Boatyard Day 19

Final day in the boatyard.

Two coats of Hempel antifouling paint applied all over. Three coats at the waterline and on the rudder.
0908FD1

It only remains to antifoul under the yard props and keel once Kiriwina is in the travel lift tomorrow morning.
0908FD2

Gelcoat repairs more or less complete and coach house/cockpit polishing completed.
0908FD3

Hull brightwork polishing completed.
0908FD4

Precision alignment of new waterline on hull and rudder.
0908FD5

A new button anode was fitted in December 2007. At haul out in May 2011 this was about 50% degraded. This anode was about 20% degraded. Worth recycling.
0908FD6

The propeller was coated with waterproof grease and the stripper will receive one coat of antifoul tomorrow morning.
0908FD7

Adjacent boats reflected on Kiriwinna's freshly polished hull.
0908FD8
The hull anode shown here was also fitted in November 2007. With only 20% degradation it was cleaned up and reused.

The rudder was secured with only one nut. Kiriwina will be moored in Piriapolis after launch and some new 21mm stainless steel nuts will be sourced and drilled in Buenos Aires. Rudder cap and tiller reinstalled.

Fenders deployed ready for launch.

Piriapolis Boatyard Day 18

Six years with Kiriwina! I took delivery at Itchenor on 8th August 2005.
1008Kav

First thing this morning the new waterline was given a final sanding and then tie coated as were other areas made good.
0808TCt

This is very good work. Imperial Yachts have taken great care to do the job thoroughly with a tight schedule and often inclement weather.
0808TCt1

The waterline before work started.
0808Bef

The boat yard shuffled the deck today and we were moved at 14:00. We took the opportunity of putting the launch back by 24 hours. Just in case.

Areas adjacent to the props were anti-fouled last night so the props could be repositioned slightly ensuring all areas of the hull are fully painted.

0808TCt2

Some final tie coating before the first coat of anti fouling.
0808TCt3

Meantime I finished cleaning and freeing up 6 A frame clamps on the Pushpit.
0808Clm

Brightwork polishing is coming along.
0808Clm1

Another long, but very productive, day. The second coat of antifouling was completed in fading light.
0808AFl
0808AFl2

Refurbished skeg and rudder heel.
0808Skg

We are almost done. Just some detailing here and there, some polishing, a bit of touching up on the anti fouling, anodes, rudder tiller assembly and we will be pretty much good to go.



Piriapolis Boatyard Day 17

Cloudy, windy and cooler today.

We are booked to launch on Tuesday. Laurence and Elise from
Imperial Yachts are working all weekend to ensure we will be ready.

With the new waterline now true a final coat of epoxy resin was carefully applied.


Newly refurbished shaft coupling with propeller shaft in situ. This was very good work. With the woodruff key in place the shaft slid home cleanly and the retaining pin located perfectly within the shaft recess.
0708Cou0708Cou1

My fourth tender bag since leaving England in 2006. The first, as supplied by Suzumar, tore the first time it was lifted. It was also too small. The second, donated in Spain late in 2006, also tore within a few weeks. The third I had made in Puerto Sherry in 2007. This gave good service but earlier this year the straps broke. Destroyed by UV.
0708Tbg

This new bag, from Dansk Canvas in San Fernando, Argentina incorporates a number of improvements. Large tooth nylon zipper with protective flap. Highest quality american UV resistant thread and UV resistant white webbing.
0708Tbg1

One never knows what will come to light while cleaning. The rudder is secured by two 21mm bolts.
This one was cracked nearly all the way through.

0708TNut0708TNut1

Piriapolis Boatyard Day 16

A really lovely day in Piriapolis.
0608Pir1

Flat calm and sunny.
0608Pir2

A sailboat leaving Piriapolis harbour for a drift about.
0608Pir3

Meantime work continued. Four coats of epoxy resin have been used to make good the faulty red gelcoat the waterline. Today this resin was sanded to form.0608Epo

Then minor imperfections were made good with epoxy filler (yellow).
0608Fil

Piriapolis Boatyard Day 14

No work yesterday due to a SE gale and heavy rain.

This morning we moved onto the final stages of epoxy buildup on the waterline and areas of hull which required refinishing.

Stern tube showing somewhat agricultural modifications to accommodate the Stripper rope cutter. Gelcoat and laminate have been hacked away unevenly with the stern tube exposed in places. We cannot source a neoprene cutlass bearing here so the original will have to suffice.

0408CutB

Epoxy resin almost complete and we now have a smart new step ladder replacing the one that failed on tuesday. Tie coat has been applied most of the hull.
0408Epo

Epoxy sanded back and surface filler applied to skeg and stern tube area.
0408Epo1

Surface filler to complete refinishing of hull blemish.
0408Epo2

Final touches to another blemish near the starboard bow.
0408Epo3

Epoxy resin waterline reconstruction at the bow.
0408Epo4

Gelcoat repairs to chips, blemishes and scratches at the bow caused by unplanned anchor contacts.
0408Gel

Piriapolis Boatyard Day 12

Weather fine and cold but still lots of progress today. One week to launch.

Most of the hull was painted with Hempel tie coat leaving only the epoxied areas. The second and third coats of epoxy resin were applied to the waterline.
0208Tc

Similar treatment on the rudder.
0208Rd

A new navy blue coach line.
0208CchLn

Refurbished and modified shaft coupling reinstalled.
0208Shc

Today's mission creep. Looks like the cutlass bearing has excessive play. Two small problems. Can we get a new one? Can we get the old one out cleanly?
0208CtB

A long spell ashore allows time for smaller repairs as well.

There are 41 brass screws in the cockpit grating and one mild steel.
0208Gr1

Good thinking. Use a mild steel under sized screw and flimsy packing so it will grip. All in a grate frequently in contact with salt water.
0208Gr2

This is what happens when wet locker hooks are not stainless steel.
0208WtLck

Today's equipment malfunction. Our one week old step ladder failed.
0208Malf